The Old Seafood Shack Lot and the Four-Year Cortez Bridge Rebuild

November 26, 2026

On the afternoon of Monday, Nov. 16, a crane on a work barge set up along the northeast side of the Cortez Bridge to drive a test piling into the bay bottom. That piling started the Florida Department of Transportation's Cortez Road Bridge Replacement Project, a 0.9-mile job that runs from 123rd Street West in Cortez to Gulf Drive in Bradenton Beach. By the time this post publishes, crews will already be off for the holiday. FDOT has suspended work from Thursday, Nov. 26, through Sunday, Nov. 29, for Thanksgiving.

FDOT's construction cost estimate is about $123 million, and the department lists the work at roughly 1,200 days. Most coverage is about the new 65-foot span. For anyone who lives on the island or in the village, though, the bigger daily story is the waterfront lot on the Cortez side, where the old Seafood Shack stood. Most of the next four years runs through that property.

Why one county lot carries so much of the work

Manatee County bought the former Seafood Shack property in 2024 for $13 million. When it was purchased, the stated plan was a public boat launch and marina. Later county talks turned to a park and possibly a Gulf Islands Ferry stop. On Oct. 20, Manatee County commissioners voted 5-1 to license the land to the bridge contractor, SEMA Construction, as a staging area for four years. Commissioner Jason Bearden cast the only no vote.

The contractor's own numbers show why the lot matters. At that meeting, a SEMA representative said the project would need more than 3,000 truckloads over the 1,200-day contract, which averages three to five a day. Without the county land, he said, the contractor would have leaned heavily on the state right-of-way in front of Tide Tables, and that would have meant daily lane closures on Cortez Road. The county's meeting background said the same thing. Staging on its land cuts down on large equipment repeatedly backing into and out of FDOT's tight right-of-way.

The agreement divides the property in two. Parcel 1, at the south end, will hold semi-permanent structures, including a crane access trestle. Parcel 2 sits along the water north of the humpback bridge on 127th Street West. SEMA said Parcel 2 would be used for employee overflow parking and for handling and storing materials. Crews would assemble forms and rebar cages there and load them straight onto barges. The area is to be fenced, gated and posted to keep the public out.

Neighbors north of the bridge will notice Parcel 2 most. As the Anna Maria Island Sun reported, residents told commissioners they had understood from a July 10 meeting that Parcel 2 would be limited to parking for light vehicles. One speaker said more than 300 residents pass the site to get in and out of neighborhoods that have one road to Cortez Road. If you live back there, plan on construction traffic at your entrance during working hours.

The lot also explains the timing. Bridge construction was supposed to start in June. It was held up because the county's new water main under the Intracoastal Waterway ran behind schedule, and the old main sat where SEMA needed to drive its first pilings. In return for using the county land, SEMA agreed not to seek delay costs from the county or the state, which a county engineer put at about $1.4 million.

Building beside a bridge that still opens

Most of the early work happens in the water, so the bridge you cross today is the 1956 drawbridge you already know. The new bridge is going up in two phases. In Phase 1, crews build the northern half right next to the existing bridge. Traffic then moves onto that new half. In Phase 2, they demolish the old bridge and build the southern half. Barges and temporary trestles carry the work in both phases. The Intracoastal Waterway stays open to boaters, and the current drawbridge opening schedule stays in effect.

Milestone Timing
Construction start Monday, Nov. 16, 2026
Thanksgiving work suspension Thursday, Nov. 26, through Sunday, Nov. 29, 2026
Phase 2 traffic shift Anticipated mid-2028
Project completion Expected summer 2030

FDOT's RoadWatch for the week of Nov. 22 lists pile driving, force main work along Hunters Point Way, temporary roadway diversions on each side of the bridge, temporary striping and barrier wall, and erosion control. Expect lane closures off and on, day and night. Night closures are planned for placing striping and barrier walls. The regular work window is 7 a.m. to 6:30 p.m., with some night and weekend shifts possible. If you walk or bike over to Bridge Street, look out for construction vehicles entering and leaving the work zone. FDOT posts weekly updates on its Cortez Bridge project page.

What will replace the bridge that rises

The new bridge is a fixed span with at least 65 feet of vertical clearance, and it sits north of the current alignment. Curves at each end bring it back onto the existing roadway. It will be 68 feet 3 inches wide, with one 12-foot travel lane each way, two 10-foot shoulders and two 10-foot sidewalks behind concrete barriers. The roadways leading to it get 6-foot bike lanes and 10-foot sidewalks. On the Cortez end, a new road called Hunters Point Way will connect Cortez Road and 127th Street West and serve the homes and businesses there.

The look of the bridge came from the people who live and work at either end of it. FDOT formed a Bridge Aesthetics Committee whose members included representatives of Tide Tables, the Seafood Shack, Bradenton Beach Marina, Cortez Park and Bridgeport Condos, along with Bradenton Beach Mayor John Chappie. The committee's recommendations include sand-colored columns, blue railings and light poles, a multi-wave pattern on the retaining walls, and four curved observation points without benches. The overlooks are planned on the north and south sides at the two piers on either side of the main channel, and the pier columns are planned with lighting on their outside faces. If you walk the bridge after 2030, the overlooks above the channel will be the places to stop.

People have mixed feelings about losing the drawbridge. In WWSB's September coverage, one Cortez resident called the rising bridge "a special part of the island life." Another local interviewed in the same story said, "I love Old Florida, and I want to keep it Old Florida. But you also have to update the infrastructure."

The same lot is where the ferry gets a base

Under the Oct. 20 agreement, SEMA is also required to build a docking, storage and fueling area for the county's Gulf Islands Ferry on the Seafood Shack property and to demolish and remove an existing house there. So the lot being used to build the new bridge will also become ferry infrastructure.

The ferry already runs. The Gulf Islands Ferry sails Thursday through Sunday between the Bradenton Riverwalk, the Historic Bridge Street Pier and Coquina Beach. The current adult fare from the Riverwalk to Bridge Street is $7 one way or $11 round trip. Riders ages 4 to 18, seniors 60 to 79 and military pay $5 one way or $7 round trip. Children 3 and under and seniors 80 and older ride free. The Coquina leg, which runs on a smaller pontoon from the Bridge Street Pier to the Coquina Bayside South Boat Ramp, is an extra $5 one way or $9 round trip for adults. Coquina tickets can also be bought alone, so you can ride from the pier to the south-end beach and back without going to downtown Bradenton. Check sailing times on the operator's site before you go, because they change by season.

The bigger boat is new this year. The Manatee Belle went into service in April 2026 with 91 seats, an enclosed climate-controlled cabin, open-air seating at the stern and public restrooms. According to Manatee County, the ferry carried more than 55,000 passengers in 2025. On Nov. 5, the Bradenton Beach City Commission voted 4-0 to set aside docking spaces at the Bradenton Beach Pier for the ferry and other water taxis.

Cortez is already planning for after the bridge

Bridge staging pushes back the county's long-term plans for the Seafood Shack property by up to four years. Some people in Cortez see that delay as time to plan. At the July 6 meeting of the Florida Institute of Saltwater Heritage, Cortez Village Historical Society vice president Paul Dreyfoos proposed a community-led concept for the property built around the idea of an eco-park. His suggested concepts include a canoe launch, boat ramp access for commercial fishers, boat-to-table food service, land- and water-based recreation and environmental education for boaters. "We don't want to let this just happen to us," he said, as the Anna Maria Island Sun reported.

Two village dates are close at hand. Christmas in Cortez is Saturday, Dec. 12, from noon to 3 p.m. on the grounds of the Florida Maritime Museum, with Santa, activities, food trucks and student performances. The museum building is undergoing a structural rehabilitation and will not be open during the event. The Cortez Commercial Fishing Festival is set for Feb. 13 and 14, 2027, from 10 a.m. to 6 p.m. both days. Both events will have the bridge work going on next door.

If you're wondering how four years of bridge work might fit with your own plans on or near The Beaches, the Argelia Vidal team would be glad to talk it through with you. Let's Connect.